By
Esther Awuah
Kweku Awotwi, VRA Boss |
Ghanaians will have to wait a little
longer as the on-going load shedding programme, which was scheduled to end in
November this year, has been extended to the first week in December.
Last week, Minister of Energy, Dr. Joe
Oteng-Adjei, announced at a news conference in Accra that the off-peak load
shedding exercise, which occurs from 6am to 6pm, would end on Monday, November
5, 2012 as a result of the completion of additional generation projects.
The peak time outage, which lasts from
6pm to 11pm, was also expected to end on November 30, 2012.
But this cannot materialise as the Volta
River Authority (VRA) is facing crude oil supply challenges from its supplier
in Nigeria.
Ghanaians have for the
past months experienced irregular power supply due to damage caused to the West
Africa Gas Pipeline (WAGP) by a vessel in August this year.
WAGP supplies gas to
some thermal plants to generate electricity.
However, Chief Executive Officer (CEO)
of VRA, Kweku Awotwi, explained that because of the current challenge “it is
expected that the load shedding would end by December should all the additional
generation come into service as scheduled.”
The additional generation projects are the steam turbine unit for Takoradi 1 Thermal Plant,
Tema Cenit Thermal Power Plant (TCTPP) owned by CENIT Energy, a subsidiary of
Social Security and National Insurance Trust (SSNIT) and two gas
turbines for the Takoradi 3 thermal project.
Mr. Awotwi further stated that supply of
crude to support the CENIT project would delay, hence the extension of the end
of the load shedding programme.
He noted that “the date for the end of
load shedding was given based on the assumption that crude oil would be in
constant supply. But we all got to know three days ago that crude oil from
Nigeria will not be supplied by November 15, 2012 as expected.”
He said the cost of importing crude was
negatively affecting the Authority, explaining that now crude oil is supplied
every 20 days, instead of the former three-month period.
Also, it costs about $50 million to take
delivery of one consignment.
Giving an update on the current
generation status, Mr. Awotwi said that all six units in Akosombo and four
thermal units in Aboadze are all running at full allowed capacity.
He added that the steam turbine in
Aboadze was also running with 50 megawatts (mw) full capacity.
He further noted that there is
sufficient crude oil to run the plants in Aboadze, and once CENIT receives its
own parcel of crude oil it can run base load at 100 mw.
He gave the assurance that “gas supply
from Nigeria is expected to be restored by December so that Sunon Asogli shall
begin to generate, bringing in 170 megawatts capacity.”
The news conference was organized in
collaboration with Ghana Grid Company (GRIDCo) and the Electricity Company of
Ghana (ECG).
No comments:
Post a Comment